Data Analysis Requirements Metrics Page

This page is used to illustrate the status of the requirements for JWST Data Analysis tools. The system is designated by the JWST Mission Office. We only follow...

The scheme for this metric tracking is that there are 4 stages of completion for a specific calibration step requirement

  • 1st stage: initial algorithm has been designed and coded
  • 2nd stage: iterations have been completed with the WIT and the current coded algorithm is believed to be what they would like (but not fully tested)
  • 3rd stage: the tool has completed testing by the developer and the WIT
  • 4th stage: the tool has been code reviewed, been documented and has regression tests

The cells in the following table are indicated to show the progress on these requirements and stages:

  • a blank cell means work has not started on this stage of the work on the requirement
  • a * means work has started
  • a date means this stage was completed on this date (resolution only to the month of completion)
REQUIREMENT Stage 1 Stage 2 Stage 3 Stage 4
(627) tools must work with FITS form 2012-01 2012-01 2012-01 2012-01
(654) tools shall use VO protocols
(629) Ability to run indiv Cal pipeline steps 2012-04
(625) ability to visualize JWST data 2012-01 2012-02 2012-03
(626) ability for arithmetic ops on data
(628) tools to compare data with models
(630) tools to register and combine data
(631) coronographic tools
(632) IFU analysis tools
(633) spectral data analysis tools
(634) instrument modeling tools
(640) distribute DA software to user